Production of solar power plants

  • Start of works: August 1, 2022.
  • Deadline for completion and commissioning: September 1, 2023.

Project description

In 2021, the company is buying a plot of 120,000 m2 in the municipality of Ulcinj. Briska gora area.

  • In this area, the State of Montenegro planned the construction of solar power plants with a capacity of 250MW.
  • Based on the survey, that area is the best in the region of Southeast Europe, because its position and amount of sunny days, 283 days a year, gives the best results for electricity production.
  • All necessary projects have been completed and approvals have been obtained for two solar power plants, one of 5mw and the other of 1mw.
  • Work on the construction of the switchboards began on August 1, 2022, with the cutting of tall and low vegetation on the plots. An access road with a length of 2400 m was also built. Geodesy was also done for further works.

Please note that this 6 mw power station is the largest in the region and is currently under construction. The deadline for the completion of works on the construction of solar power plants and their commissioning is September 1, 2023. Stanko invest continues with further investments in Serbia in the construction of solar power plants.